1.  40 men build a wall 4 meters high in 15 days. The number of men required to build a similar wall 5 meters high in 6 days would be
(1)115                                           (2) 105                 
(3)135                                           (4)125                  
(5) None of These

2.  If 24 men can do a piece  of  work in 27  days  working  7  hours  per  day,  in how  many  days  can  14 men do it working at the rate of 9 hours per day?
(1) 30                                             (2) 8                      
(3) 32                                             (4) 36                    
(5) None of These

3.   A  200  m  long  2  m  high  and  40  cm  wide  wall  is  built  by  20  men,  30  women  and  60  children working 6 hours a day in 20 days. How long a wall 1. 5 m high 60 cm wide can  be built by 10 men, 15 women, 30 children working 9 hours a day in 15 days?
(1)75 m                                         (2)150 m             
(3)225 m                                      (4)166. 66 m      
(4)None of These

4.   A  150m  by  20m trench of depth 1.  5m is  dug by  16 men  in 10 days. A trench twice  the  length  & one-third the depth but thrice the width can be dug by half the men in how many days?
(1)40                                              (2) 30                    
(3)20                                              (4)10
(5)None of These

5.   7 women and 6 men can do what 4  men and 11 women can do in the same  time.  19 women can do the same job in how much time?
(1) same                                      (2) half                 
(3)one-third                               (4) two-third     
(5) None of These

6.   If A can walk a certain distance in 40 days when he takes rest 9 hours each day;  how much long will he take to walk the same distance twice as fast and rest twice as long each day?
(1) 50 days                                  (2) 45 days         
(3) 38 days                                  (4)16 days          
(5)None of These

7.   If 20 men or 25  women or 30 boys can do  a piece of work in 16 days by working 10 hours a day, then  how many men  with 10  women and  18  boys can do 3 1/4 times the  same work in  26  days by working 8 hours daily?
(1)35 men                                   (2)30 men          
(3) 40 men                                  (4)48 men          
(5) None of These

8.  Some persons can do a job in 12 days. Two times the number of those persons will do half of that job in
(1) 6 days                                     (2) 4 days            
(3) 12 days                                  (4)3 days             
(5) None of These

9.  400  men working  9  hrs a  day  complete  ¼ th  of  the  work  in 10  days.  The number of  additional men, working 8 hrs a day, required to done the remaining work in 20 days is
(1) 675                                          (2)275                  
(3) 250                                          (4)225                  
(5)None of These

10.   If 24 men working 8 hours a day can do half a piece of work in 9 days, in how many days will 36 men working 12 hours a day finish one-third the same work?
(1) 2 days                                     (2) 2 2/3 days    
(3) 3 1/3 days                             (4)4 days             

(5) None of These


Click here to Get Answers:
Question 1:
Question 2:
Question 3:
Question 4:
Question 5:
Question 6:
Question 7:
Question 8:
Question 9:
Question 10:
Quantitative Quiz - Competitive Exams - IBPS/BANKING EXAMS - 20 Quantitative Quiz - Competitive Exams -  IBPS/BANKING EXAMS - 20 Reviewed by Job today on 08:44 Rating: 5

No comments:

Powered by Blogger.